Refurbishment BMW FIZ, Munich

Sanierung BMW FIZ, München

Bauherr:

BMW AG

Architekt:

Henn Architekten

Fassadenberater:

DS-Plan

Baujahr:

Aug. 2015 – Okt. 2015

Refurbishment BMW FIZ, Munich

Extensive modernisation works of the Research and Innovation Centre.

BWM Group’s Research and Innovation Centre was being planned from 1983 onwards, 1986 the first construction stages were ready for occupation. Already in those days parts of the façades were supplied by Dobler Metallbau. A complete refurbishment of the entrance building in 2014 was the beginning of extensive modernisation works, which are carried out step by step on all buildings. In doing so the office infrastructure is adapted to today’s technical requirements.

Thanks to the proven proprietary fittings and system technology Dobler Metallbau was also selected to refurbish the façade. During these works thousands of windows casements were replaced, among other works.

Works:

During refurbishment of BMW AG’s Research and Innovation Centre, window casements were replaced across 9 construction stages.
Approx. 9,000 windows (approx. 9,000 windows in each construction stage)