Vodafone Campus, Düsseldorf
Building owner:
Objekt Düsseldorf VCD-Realisierungs-GmbH & Co.KG
Client:
ARGE Vodafone Campus, Düsseldorf (Zechbau & Ed Züblin AG)
Planning architect/Site supervision:
HPP Hentrich–Petschnigg & Partner GmbH + Co. KG, Düsseldorf
Facade consultant:
InFaCon GmbH, Cologne
Installation time:
8 months
Facade area & quantity:
33,400 m² unitised facade
3,800 m² stick system
Facade handover:
2012
Dobler Metallbau executed the order in a joint venture with Scheffer Metallbau GmbH and was responsible for two low-rise buildings and the high-rise building. The order was placed on 7 May 2011, and the façade was impermeably sealed according to contractual specifications at the end of the year. Approx. 37,000 m² façade in only 8 months from planning to installation of the completely pre-fabricated elements. An outstanding effort which makes everyone involved, not least because of the observed quality standards, really proud.
Broschure // Download
(PDF-file, 1128 KB)